IP 15-year Playground Replacement

Parks and Recreation

Time Status:

Budget Status:

Percent Complete: 85%

Start Date: 10/01/2019

End Date: 09/30/2025

This project is to replace the City's Park's playgrounds on a 15- year cycle.

Playground structure has been ordered for Westchester Park, staff anticipates delivery in March 2022, with an install of April 2022. 

Operating Budget:
Capital Budget:
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined