Select Page

Time Status:

Budget Status:

Percent Complete: 100%

Start Date: 10/01/2022

End Date: 06/30/2024

The installation of fitness elements at Riverside Park will enhance the community’s quality of life through areas of wellness, health, and socialization. The fitness area will offer a unique mix of fitness opportunities, contributing towards the community’s wellness, physical and social health.

The project is complete. The Certificate of completion issued for the new bathrooms and expanded parking lot is open for use. Solar workstations for social spaces have been installed. Project included the install of a new playground, fitness stations, and a ninja course.

Operating Budget: $0
Capital Budget: $700,000 (ARPA Funding)
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined

City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000