Time Status:

Budget Status:

Percent Complete: 75%

Start Date: 10/01/2022

End Date: 11/30/2023

The installation of fitness elements at Riverside Park will enhance the community’s quality of life through areas of wellness, health, and socialization. The fitness area will offer a unique mix of fitness opportunities, contributing towards the community’s wellness, physical and social health.

Concession stand conversion to restrooms is underway, contractor has began demo work. Expectation is to have the restrooms complete within 60 days.

 

Pickleball stadium shade canopies are starting Monday 3/4 and will be complete by Friday 3/8

 

Basketball court fencing installation began yesterday, contractor should be finished by Tuesday 3/5 and we can get the basketball court opened for use.

 

Staff will remove the old playground in mid/late-march so we can begin the social space area.

Operating Budget: $0
Capital Budget: $700,000 (ARPA Funding)
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined

City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000