Time Status:

Budget Status:

Percent Complete: 50%

Start Date: 10/01/2018

End Date: 12/31/2026

City staff is working closely with the City Village developer to bring this mixed-use project to fruition. The development will include retail, restaurants, residential and office space on the northwest corner of University Drive and Sample Road.

The project submitted for P&Z. Working with the Developer to discuss other opportunities for the project. There are 28 special exceptions and staff is not recommending approval.

Operating Budget: $ 0.00
Capital Budget: $ 0.00
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined

City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000