Time Status:

Budget Status:

Percent Complete: 25%

Start Date: 10/01/2021

End Date: 09/30/2023

An element of the city’s Strategic Plan is the use of renewable energy. The installation of environmentally beneficial technologies, like solar power, would provide the community safe and attractive facilities, while avoiding disruptive construction and costly monthly energy bills. City staff is developing an initiative for the installation of solar power in city parks, including hiring a consultant to review possibilities for solar in parks and other city properties.

Solar in the park projects identified under this initiative include:

  • Mullins Park Umbrella Charging Stations - Complete
  • Dog Park Vending Machine - Machine has been installed, vendor is at risk and has till August 31, 2023 to get the machine operational. If not operational the contract will be canceled. 
  • Cypress East Lighting: In progress. Staff met with the vendors for quotation information regarding Solar Pathway Lighting.
  • AED's in the Park: Complete, 9 of the 30 machines have a solar component. 
Operating Budget:
Capital Budget:
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined