ARPA: Redevelop Kiwanis Park
Parks & Recreation
Time Status:
Budget Status:
Percent Complete: 25%
Start Date: 10/01/2021
End Date: 01/31/2025
Improvements to Kiwanis Park site will offer a raised walking path, nature garden, new pavilion, and playground to provide activities to the community of all ages.
Pavilion and playground are installed. Environmental assessments are completed and the new boardwalk is in design.
Operating Budget:
Capital Budget:
Capital Budget:
Legend:
Initiatives: Closed Out/Completed | On Target/In Progress | Behind Schedule/Late | Discussion Needed Retreat/Workshop Item | Delay/Hold | No Milestone | Not Defined
Initiatives: Closed Out/Completed | On Target/In Progress | Behind Schedule/Late | Discussion Needed Retreat/Workshop Item | Delay/Hold | No Milestone | Not Defined
Legend:
Initiatives: Closed Out/Completed | On Target/In Progress | Behind Schedule/Late | Discussion Needed | Retreat/Workshop Item | Delay/Hold | No Milestone | Not Defined
Initiatives: Closed Out/Completed | On Target/In Progress | Behind Schedule/Late | Discussion Needed | Retreat/Workshop Item | Delay/Hold | No Milestone | Not Defined