ARPA: Redevelop Kiwanis Park
Parks & Recreation
Time Status:
Budget Status:
Percent Complete: 25%
Start Date: 10/01/2021
End Date: 09/30/2024
A new playground and pavilion have been installed. An asphalt pathway has been installed to provide ADA access to the playground.
A grant has been received to construct a new boardwalk trough and around the forested area. Staff will be working to develop budgets to determine funding needed. Staff are working with an architectural firm to develop plans and comply with all regulations regarding the construction of the boardwalk in the conservation area.
Other enhancements to the park will be made in later phases after the current Fire Station 64 is renovated in to a Senior/Community center.