Stormwater Improvements in Westchester
Public Works
Time Status:
Budget Status:
Percent Complete: 60%
Start Date: 10/01/2021
End Date: 09/30/2025
City staff is working to improve the stormwater system/infrastructure and mitigate flooding in the Westchester neighborhood, between Sample Road and Royal Palm Boulevard and Coral Ridge Drive and NW 123rd Avenue. City staff will design the second phase of the Westchester stormwater improvement project, as recommended in the design report.
Phase 1: Study - Complete (FY23)
Phase 2: Design - In progress (FY24)
Phase 3: Construction (FY25)
Grant funding has been awarded by the Environmental Protection Agency (EPA). Project to begin in March.
Operating Budget:
Capital Budget:
Capital Budget:
Legend:
Initiatives: Closed Out/Completed | On Target/In Progress | Behind Schedule/Late | Discussion Needed Retreat/Workshop Item | Delay/Hold | No Milestone | Not Defined
Initiatives: Closed Out/Completed | On Target/In Progress | Behind Schedule/Late | Discussion Needed Retreat/Workshop Item | Delay/Hold | No Milestone | Not Defined
Legend:
Initiatives: Closed Out/Completed | On Target/In Progress | Behind Schedule/Late | Discussion Needed | Retreat/Workshop Item | Delay/Hold | No Milestone | Not Defined
Initiatives: Closed Out/Completed | On Target/In Progress | Behind Schedule/Late | Discussion Needed | Retreat/Workshop Item | Delay/Hold | No Milestone | Not Defined
City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000