Time Status:

Budget Status:

Percent Complete: 58%

Start Date: 10/01/2018

End Date: 09/30/2020

Each year, the City is required to complete an Action Plan as a part of the Community Development Block Grant (CDBG) program, provided through the Department of Housing and Urban Development. The plan describes specific projects and activities the City will undertake in the coming year to address priority needs identified in the 2015-2020 Consolidated Plan. These priorities include providing a suitable living environment, providing decent and affordable housing, and expanding economic opportunities.  The City’s five-year Consolidated Plan has the framework for the City’s annual Action Plan to identify housing, homelessness, community and economic development needs and resources, and then tailor a strategic plan to meet those needs.


The program allows the City to utilize grant funds for capital improvement projects in the City’s low- to moderate-income areas which otherwise would have to be paid through the City’s Capital Improvement Program and allows 15% of the funding for public services (senior and youth programs). The following projects are listed in the Fiscal Year 2019/2020 Action Plan:

• NW 28th Street Sidewalk Replacement: $120,000
• Lion Park Lighting Project: $100,000
• Castlewood Park Replacement: $85,000
• NW 27th Street Sidewalk Replacement: $70,000
• NW 24th Street Sidewalk Replacement: $60,000
• Youth Scholarship Program: $50,000
• Home Repair: $40,043
• Senior Recreation and Functional Training: $40,000
• Senior Recreation and Therapeutic Program: $24,241
• Ramblewood ADA Sidewalk Study: $20,000
• Planning and Administration: $152,321


This initiative is an "ongoing" initiative. The budget listed is for one year. The budget for subsequent years will be approved by the City Commission during the budget process. 


Home Repair applicants have been income verified and construction is currently taking place.  Projects are within budget and 58% of the total Annual Action Plan funds have been expended. 

City Commission approved a substantial change on May 20th of FY2020 to reallocate funds for  sidewalk design projects.

Operating Budget: $ 154,038.00
Capital Budget: $ 616,153.00
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined

City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000