Select Page

Time Status:

Budget Status:

Percent Complete: 15%

Start Date: 11/01/2024

End Date: 09/30/2028

To evaluate the vacate land and current facilities located in the Sportsplex area for the best use providing a premier value to the residents, businesses, and visitors to the City of Coral Springs.

Project is moving into the design phase. Staff completed RFP's for architectural services. Item presented to Commission 8/5/2026, item to be represented in November 2026.

Operating Budget: Existing Funds
Capital Budget: $0
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined