Stormwater Improvements in Meadow and the Dells Phase B & C
Public Works
Time Status:
Budget Status:
Percent Complete: 100%
Start Date: 10/01/2021
End Date: 05/31/2024
Drainage improvements are needed in the Meadows and Dells neighborhoods to improve the accumulation and distribution of stormwater and avoid any possible flooding in the area due to heavy rainfall. The purpose of this project is to improve the existing drainage system and increase storage capacity within the basins. In doing so, this project will eliminate standing water and provide flood mitigation with the occurrence of heavy rainfall. This is the third and final phase of the Meadows and Dells Stormwater Improvement project. The project is located in the area between NW 44th Court and NW 41st Circle and NW 76th Avenue and NW 75th Avenue.
Drainage improvements with the Meadows and Dell neighborhood project has been completed.
Operating Budget: $0
Capital Budget: Existing Funds
Capital Budget: Existing Funds
Legend:
Initiatives: Closed Out/Completed | On Target/In Progress | Behind Schedule/Late | Discussion Needed Retreat/Workshop Item | Delay/Hold | No Milestone | Not Defined
Initiatives: Closed Out/Completed | On Target/In Progress | Behind Schedule/Late | Discussion Needed Retreat/Workshop Item | Delay/Hold | No Milestone | Not Defined
Legend:
Initiatives: Closed Out/Completed | On Target/In Progress | Behind Schedule/Late | Discussion Needed | Retreat/Workshop Item | Delay/Hold | No Milestone | Not Defined
Initiatives: Closed Out/Completed | On Target/In Progress | Behind Schedule/Late | Discussion Needed | Retreat/Workshop Item | Delay/Hold | No Milestone | Not Defined
City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000