IP Address Sidewalk Replacement & ADA Streets

Public Works

Time Status:

Budget Status:

Percent Complete: 52%

Start Date: 10/01/2024

End Date: 09/30/2025

Project consists of replacing existing asphalt sidewalks with concrete sidewalks and replacing existing ramps for ADA compliance. Sidewalk and ADA ramps will be replaced on Westview Drive from Riverside Drive to Coral Ridge Drive, and along NW 107th Drive.

The contractor has updated the sidewalk on the North side of Westview and is 50% complete with the project. 

Operating Budget:
Capital Budget: $3,000,000 (ARPA Funding)
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined

City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000