Stormwater Improvements in Westchester
Public Works
Time Status:
Budget Status:
Percent Complete: 65%
Start Date: 10/01/2024
End Date: 09/30/2026
City staff is working to improve the stormwater system/infrastructure and mitigate flooding in the Westchester neighborhood, between Sample Road and Royal Palm Boulevard and Coral Ridge Drive and NW 123rd Avenue. City staff will design the second phase of the Westchester stormwater improvement project, as recommended in the design report. Phase 1: Study - Complete (FY23) Phase 2: Design - In progress (FY24) Phase 3: Construction (FY25)
Staff is pending progress on this project due to FPL & AT&T lines within the project site. Staff is reporting potential delays to FDEP for grant reporting.
Operating Budget: $0
Capital Budget: Existing Funds
Capital Budget: Existing Funds
Legend:
Initiatives:
Closed Out/Completed |
On Target/In Progress |
Behind Schedule/Late |
Discussion Needed
Retreat/Workshop Item |
Delay/Hold |
No Milestone |
Not Defined
Initiatives:
Legend:
Initiatives:
Closed Out/Completed |
On Target/In Progress |
Behind Schedule/Late |
Discussion Needed |
Retreat/Workshop Item |
Delay/Hold |
No Milestone |
Not Defined
Initiatives:
City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000