IP Corporate Park Improvements (2017-2020) (Ongoing)

Economic Development

Time Status:

Budget Status:

Percent Complete: 40%

Start Date: 10/01/2018

End Date: 09/30/2020

The City and Property Owners of the Coral Springs Corporate Park Association have created a stronger dialogue, working cooperatively to address long-standing issues in the Corporate Park. City staff, the Association, the Coral Springs Regional Chamber, and Sunshine Water Control District continue to meet on a quarterly basis to discuss areas of concern. The City has also explored grant funding to address the drainage issues in the Park. The City will continue building solid, productive relationships and partnerships with existing and new companies in the Corporate Park to make it a better place to work and do business.

The stormwater improvements in the CP associated with the EDA grant are on schedule. The Corporate Park Association met on June 26th to hear from Chen Moore about the project. The design plans were sent out for comment from the Association.

Operating Budget: $ 0.00
Capital Budget: $ 0.00
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined

City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000