Select Page

IP Village Square Redevelopment (Ongoing): Form City Village Plan with Developer

Economic Development

Time Status:

Budget Status:

Percent Complete: 25%

Start Date: 10/01/2018

End Date: 09/30/2021

The Economic Development Office (EDO) is working with the Community Redevelopment Agency (CRA), Development Services and the developer of Village Square to ensure that the project fits the Downtown Mixed-Use Zoning approved in January 2018. The development will include retail, restaurants and office space on the northwest corner of University Drive and Sample Road.

Village Square is now called City Village. Meeting held with the developer on June 3rd to discuss DRC comments. Staff has also asked for a timeline for the project. They are currently in lease negotiations with the grocer.

Operating Budget: $ 0.00
Capital Budget:
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined

City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000