Select Page

Time Status:

Budget Status:

Percent Complete: 100%

Start Date: 10/01/2019

End Date: 09/30/2020

Galvanized water service lines account for most customer complaints received by the Utilities Division. Leaks and breaks due to corrosion increase the City’s operating costs and decrease revenue caused by water loss. It is also possible that lines could be completely blocked and cease the flow of water due to the constriction of the galvanized water lines. An ongoing program to replace the existing galvanized water pipes throughout the City’s utility service area ensures proper flow of water and effective operation of these galvanized water lines.

The replacement of section 20 water service lines is completed. 

Operating Budget:
Capital Budget:
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined

City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000