Time Status:

Budget Status:

Percent Complete: 90%

Start Date: 10/01/2020

End Date: 12/30/2021

This project is the improvement of five (5) lift stations. This rehabilitation prevents sewer overflows and provides a reliable wastewater collection system.

Lift stations 14A and 19C are 100% complete. 

Lift Station 15C is 98% complete. Sidewalk repair pending

Lift Station 20C is 98% complete. Connected to FPL power 

Lift Station 17B is 85% complete. It is still on bypass pumping and MOT was removed. Fence and sod was installed

Operating Budget:
Capital Budget:
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined

City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000