Time Status:

Budget Status:

Percent Complete: 100%

Start Date: 10/01/2018

End Date: 09/30/2019

This project is to replace the 25 Meter Pool Liner at the Aquatic Complex. The Pool Liner covers the walls and floor of the pool to protect the shell from developing cracks and leaks. The current liner is over 22 years old and the average life expectancy of a liner is 15 to 20 years. The 25 Meter Pool is used for swim meets, synchronized swimming, water polo, swim lessons and public swimming.

The pool liner has been upgraded. This project is complete.

Operating Budget: $ 0.00
Capital Budget: $ 350,000.00
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined

City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000