Select Page

C 15-year Playground Replacement: Riverside Park (FY23)

Parks & Recreation

Time Status:

Budget Status:

Percent Complete: 100%

Start Date: 10/01/2022

End Date: 01/31/2024

This project is for the ongoing replacement of city park playgrounds on a 15- year cycle.

Construction of the new playground at Riverside Park has been completed and the playground is now open for play. 

Operating Budget:
Capital Budget:
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion NeededR/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined
Legend:  
Initiatives: On Target Closed Out/Completed | IP On Target/In Progress | Below Plan Behind Schedule/Late | DN Discussion Needed | R/W Retreat/Workshop Item | D Delay/Hold | N No Milestone | Not Defined Not Defined

City of Coral Springs | 9500 West Sample Road, Coral Springs, FL 33065 | 954-344-1000